DOC13.3

EXECUTIVE SUMMARY

The aim of the DER-IREC 22 @ Microgrid project is to implement a micro grid at IREC facilities in Barcelona, which is connected to ENDESA’s distribution network and incorporates the electric vehicle as specific load.

This deliverable entitled "Implementation and verification of power converters hardware” is part of the work package PT130 which is entitled "Microgrid assets measurements and control" that is contained within the work package PT100 coordinated by CIRCUTOR and deals with the study of the control and measurements architecture in the microgrid. 

The present document shows the tests and changes made to the power converters in the manufacturing process and its implementation in the IREC’s facilities.